|
Photo Galleries |
 |
JEFF
BURTON FIRST NASCAR DRIVER TO SEE NEW SURFACE AT DARLINGTON RACEWAY
DARLINGTON, S.C. (Feb. 20, 2008) – Construction crews working to repave
Darlington Raceway received a visit from NASCAR Sprint Cup Series driver
Jeff Burton on Wednesday. Burton, driver of the No. 31 AT&T Mobility Richard
Childress Racing entry, spent time talking with the crew working on the project
and then went to work himself, driving a milling machine in turn 3. “I
have never driven so slow at Darlington,” joked Burton after he finished
milling the asphalt in turn 3. “A project of this magnitude shows a
commitment to Darlington Raceway, and that is something that race fans everywhere
should be very pleased with.” Burton, winner of the 50th Southern 500
(August 22, 1999), was also presented with a historic piece of the start-finish
line by Darlington Raceway President, Chris Browning. “Jeff has been
one of Darlington Raceway’s biggest fans,” said Browning. “His
milestone win in the 50th Southern 500 was part of a season sweep that he
accomplished in 1999 at Darlington, and it seemed fitting that he receive
a piece of the historic start-finish line.” “I consider winning
the 50th Southern 500 at Darlington Raceway the biggest win of my career,” said
Burton. “Winning at Darlington is more than a trip to victory lane
and a trophy; it means your name goes down in the record books as a winner
at one of NASCAR’s most historic tracks.” Don’t miss your
chance to see Jeff Burton and the stars of the NASCAR Sprint Cup Series as
they take on the track “Too Tough to Tame” in the Dodge Challenger
500 on May 10, 2008. The racing action kicks off with the NASCAR Nationwide
Series Diamond Hill Plywood 200 on 9th. Order your tickets and Colvin Grill
all-you-can-eat package now by calling 1-866-459-RACE or logging onto http://www.racetickets.com. |
 |
Darlington
Repaving Project - Week 34
Darlington, S.C. (Feb. 4, 2008) - The infamous wall that has dashed so
many Darlington dreams and caused countless "Darlington Stripes" began
to take shape on Monday as crews re-assembled the outer SAFER barrier wall at
Darlington Raceway.
Paving began at the track “Too Tough to Tame” in the mid January
and with the outer groove of the track complete, construction crews are now focusing
on finishing the racing surface and infield access tunnel in advance of the 2008
Dodge Challenger 500.
The new asphalt surface at Darlington Raceway is part of a $10 million dollar
capital improvement project that began following the 2007 Dodge Avenger 500.
In addition to the new racing surface, work is also underway to complete a new
infield access tunnel large enough to accommodate race car haulers, motorcoaches
and emergency vehicles.
Don't miss your chance to see the stars of the NASCAR Sprint Cup Series
as they take on the track “Too Tough to Tame” in the Dodge Challenger
500 on May 10, 2008. The racing action kicks off with the USAC Silver Crown Series
and the NASCAR Nationwide Series Diamond Hill Plywood 200 on May 8th and 9th,
respectively. Order your tickets and Colvin Grill all-you-can-eat package now
by calling 1-866-459-RACE or logging onto http://www.racetickets.com. |
 |
Darlington
Repaving Project - Week 32
Crews work to pave pit road at Darlington Raceway. In addition to the new
asphalt, new concrete pit boxes have been added.
|
 |
Darlington
Repaving Project - Week 31
Engine noise could be heard coming from historic Darlington Raceway on Monday
well in advance of the 2008 Dodge Challenger 500. The engine noise came not
from race cars, but from construction equipment being used to lay the first
of two layers of new asphalt at the track "Too
Tough to Tame."
"This is a historic day for Darlington Raceway," said Chris Browning,
Darlington Raceway President. "It has been a busy off-season at
Darlington Raceway and we look forward to showcasing our new racing surface
and infield access tunnel for fans and competitors during the upcoming Dodge
Challenger 500 weekend."
The new asphalt surface at Darlington Raceway is part of a $10 million
dollar capital improvement project that began following the 2007 Dodge Avenger
500. In addition to the new racing surface work is also underway to complete
a new infield access tunnel large enough to accommodate race car haulers,
motorcoaches and emergency vehicles.
Don't miss your chance to see the stars of the NASCAR Sprint Cup Series
as they take on the track "Too Tough to Tame" in the Dodge Challenger
500 on May 10, 2008. The racing action kicks off with the USAC Silver Crown
Series and the NASCAR Nationwide Series Diamond Hill Plywood 200 on May 8th
and 9th, respectively. Order your tickets now by calling 1-866-459-RACE or
logging onto http://www.racetickets.com. |
 |
Darlington
Repaving Project - Week 30
Backfilling Begins at Darlington Raceway Darlington, S.C. (January 7, 2008) - Construction
crews were busy at work Monday at Darlington Raceway as they began to backfill
dirt around the newly constructed infield access tunnel. In addition to backfilling
around the tunnel, crews are also busy water-proofing the top and sides of the
newly constructed tunnel as well as adding concrete forms for the winged walls
on the tunnel's infield entrance/exit.
|
 |
Darlington
Repaving Project
- Week 23
In Week 23, the project pace has hit a new gear, as the pre-cast tunnel roof
sections have begun to be placed, milling has begun on the actual race surface,
and the existing tunnels have been reinforced to handle upcoming track paving
operations.
|
 |
Darlington
Repaving Project
- Week 22
The milling of pit road and pouring of concrete pit stalls continues.
|
 |
Darlington
Repaving Project
- Week 20 & 21
Tunnel floor concrete slabs and seven foot sections of tunnel wall continue to
be poured. The tunnel roof should be put on at the beginning of next week.
The asphalt pit boxes were removed at the end of last week and the team is
replacing them with a concrete surface. Using concrete versus asphalt will
eliminate the damage caused by fuel, oils and other miscellaneous substances
that are left behind.
|
 |
Darlington
Repaving Project
- Week 19
Additional sections of the tunnel floor were being poured at the end of last
week. The paving process started on Friday with the team putting down test
strips. The milling of pit road began over the weekend and will continue
throughout the week.
|
 |
Darlington
Repaving Project
- Week 18 Sections of the tunnel floor are now being poured.
|
 |
Darlington
Repaving Project
- Week 17 Prepping for the pouring of the tunnel floor.
|
 |
Darlington
Repaving Project
- Week 16 Today, concrete was poured to hold the wet well, beneath the
tunnel floor, in place. The wet well is the area where rain water is collected
and pumped out. This process was completed today.
|
 |
Darlington
Repaving Project
- Week 15 On Monday, a few feet of concrete for the tunnel floor will
be poured. The team has finished excavation, so everything will be "uphill" from
here.
|
 |
Darlington
Repaving Project
- Week 14
It's a busy week at the track "Too Tough To Tame."
The construction team is currently laying black fabric on the bottom of the
tunnel hole. One foot of stone is being put on top of that fabric and will be
wrapped in geogrid (waterproofing) material. These steps should be completed by
the end of the week.
The milling process should begin in approximately one month. Milling consists of
grating the tracks surface 3 to 4 inches down and must take place prior to
repaving.
|
 |
Darlington
Repaving Project
- Week 13
Phase III excavation for the tunnel will take place for the next 2 days.
Next, the team will place stone bedding in the bottom of the tunnel foundation.
This is a one day process.
On Monday, the installation of the waterproofing will begin. The main focus next
week will be finding a location for the wet well, a permanent system that pumps
rain runoff out of the tunnel.
|
 |
Darlington
Repaving Project
- Week 12
The team continues to insert the final tie backs and expect the project to
be completed by beginning of next week. Once completed, phase III excavation
will take place for 1 to 2 days.
The next steps involve the tunnel floor. Workers will put down one foot of
stone, wrapped in fabric, to build a stable base in the bottom of the hole.
Waterproofing will be inserted and rebar will be placed on top of it. They will
then be ready to pour 2.5 ft of concrete to serve as the base for the tunnel
floor. This project is about 3 weeks away. The milling of the track's asphalt
will start in approximately one month.
|
 |
Darlington
Repaving Project
- Week 11
The main operation this week is continuing the installation of tie backs.
These are 80 foot long rods that are drilled into the earth to stabilize the
embankment of the tunnel. Once the final tie backs are installed there will be
several more days of excavation. This leads the construction team to the
beginning stages of inserting the tunnel floor.
|
 |
Darlington
Repaving Project
- Week 10
The main operation this week is installation of additional tie backs. Tie
backs are approximately 80 ft long rods that are inserted into holes drilled in
the embankment to allow the structure stability.
More excavation has taken place the last two days in order to get to the correct
elevation to insert these tie backs. Once the tie backs are installed there will
be a few more days of excavation and then inspections will take place to assure
the tunnel can be supported.
|
 |
Darlington
Repaving Project
- Week 9
We are currently installing well points to dewater the tunnel for
excavation. This process should be completed by the end of the week. The asphalt
plant is set up and Phase II Excavation and installation of sheeting tiebacks
will begin early next week and last for approximately one week.
|
 |
Darlington
Repaving Project
- Week 8
In Week 8, crews continued driving sheets to stabilize the ground for Phase
2 excavation. In addition, the on-site asphalt plant was constructed
|
 |
Darlington
Repaving Project
- Week 7
Phase 1 of tunnel excavation was completed this week and the crew began to
drive sheets to stabilize the ground for Phase 2 excavation
|
 |
Darlington
Repaving Project
- Week 6
Excavating to make way for the new infield access tunnel continues.
|
| |
 |
Darlington
Repaving Project
- Week 5
The track is leveled to make way for the new tunnel, which will sit
approximately 35 feet below the current surface.
|
|
 |
Darlington
Repaving Project - Media Day
Darlington Raceway president Chris Browning was joined by Harold Brasington
III and Jim and John Ramsey for an official groundbreaking on July 18.
|
|
 |
Darlington
Repaving Project - Week 1
Removal of the track's SAFER (Steel and Foam Energy Reduction) barriers,
which were installed in 2004
|
|
| |